Hart
County Five Year Road Plan
Jon Caime, Hart County Public Works Director
January 28, 2003
Executive Summary:
Hart County has an estimated $80,000,000 in road assets including
224 bridge structures, 356 miles of asphalt paved roads, 92 miles
of tar and gravel paved roads, and 109 miles of gravel roads. This
plan addresses the roads only and a future plan will address the
County’s bridge structures.
The value of our road assets has declined due to
a lack of a long range plan, neglected maintenance (including resurfacing),
and lack of sufficient resources. Currently this plan estimates
$7,500,000 in neglected paved road work and an annual investment
of over $1,250,000 thereafter to maintain our paved road assets
at their current value.
This 5 year plan recommends sealing all asphalt
paved roads in year 1 (FY03) at a cost of $387,748 using the road
department. By stabilizing the asphalt paved roads this plan assumes
the $7,500,000 neglected paved road work will not increase over
the five year planning period.
The County has also 92 miles of tar and gravel surfaced
roads in various stages of degradation. All these roads are past
their design surface life so this plan recommends resealing all
92 miles of tar and gravel roads over the five year planning period.
This is estimated to cost $140,000 annually in materials using the
road department and will begin in FY03. The current replacement
value estimate for the tar and gravel surfaced roads is $3,220,000.
If no action is taken to resurface these roads it is estimated that
$1,452,500 of tar and gravel road surface will be lost over the
five year planning period.
The bridge component of the long range plan is in
the process of being finalized however it is estimated that over
$600,000 is needed to stabilize our bridge structures over the five
year planning period. This investment will preserve over $9,500,000
in bridge structures.
Note on costs- all dollar values presented are 2002 estimated dollars
and cost of money considerations are not included for future dollar
estimates.
ASPHALT PAVED ROADS
Ranking System:
Hart County’s pavement management program used a similar rating
system as the GA DOT system. This system is comprehensive and by
utilizing this system Hart County can select roads that will rank
higher on the GA DOT system for those roads that the County desires
to submit for the various State assistance programs.
This system has basically four parts ranking the condition of the
pavement, use of the road (traffic volume), number of structures
per mile, and a minor score for the road based on the road’s
importance to the road system. This plan ranked each paved road
based on these factors and also included a 5th factor for the pavement
condition.
This 5th factor determined the amount of two types
of cracks that are primarily observed on aged pavements. The first
is called transverse and longitudinal cracking (T&L cracking)
which are longer widely spaced cracks both parallel and perpendicular
in the road pavement. This type of cracking is normally early evidence
of future further pavement degradation.
If these cracks are sealed then water can not enter
the subsurface below. If water is allowed to enter the subsurface
below, the supporting structure of the pavement (base & sub
base) weakens causing further cracking.
This further cracking as well as other conditions
such as bad base/sub base and truck traffic leads to the second
type of cracking which is referred to alligator cracking. These
issues are further discussed in the pavement maintenance section
of this report. This 5th factor was utilized to divide Hart County
paved roads into 5 categories (excellent, good, fair, poor, very
poor).
Roads will also be divided into six classes depending
on the type of road, traffic, truck traffic. This is important in
determining factors such as paint stripping, reconstructing of base,
prioritization etc. Classes will be listed as A,B or C depending
on the volume of traffic with an A class road having higher traffic.
A number will also be assigned to the ABC classification
to define the amount of heavy truck traffic anticipated. Roads that
will have heavy truck traffic will be assigned a 2. These roads
may need additional base materials when reconstructed.
Causes for Paved Road Degradation:
It is important to understand how paved roads degrade as well as
some factors involved in pavement degradation. As shown in figure
1 roads fail for a variety of reasons. Any pavement failure must
be corrected and patched prior to resurfacing the road or the pavement
failure will appear in the new road in a short period of just a
few years. Patching is a costly endeavor estimated to cost approximately
$16 per square yard.
Example 1 (Figure
1), shows one type of failure where a tree root enters below
the pavement and pushes up the pavement. This type of defect can
be corrected by cutting down the tree or cutting the tree root outside
the pavement. The damaged area will most likely require patching
prior to resurfacing the road.
Example 2 (Figure
1), shows another type of failure
where the pavement has degraded through aging of the pavement. As
the pavement ages it gets brittle and cracks. These cracks must
be sealed to prevent further more costly damage where water enters
the base and sub base below the pavement. Depending on the extent
and type of cracking, the damaged area may require patching prior
to resurfacing the road.
Example 3 (Figure
1), shows another type of failure
where no base (or insufficient base) was placed under the pavement
when the road was constructed. Asphalt has limited structural capacity
at the thicknesses normally placed for surface pavement. Therefore
a compacted sub base (dirt) and compacted base (normally stone)
must be placed prior to placing an asphalt surface.
When a paved road does not have sufficient base,
the road may degrade with loading causing the pavement to fail.
The damaged area must be removed and patched prior to resurfacing
the road. If the road has been allowed to fail greater than 20%
of the road surface and/or the road has excessive loads from heavy
trucks, complete replacement of the pavement and base should occur.
To remove the existing pavement, place a new gravel
base and pave a road will cost an average $167,000 per mile. There
are other methods to recycle the existing pavement by grinding or
milling the existing pavement and add additives prior to placing
a new road surface. This method can reduce costs to $100,000 per
mile.
Example 4 (Figure
1), shows another type of failure
where that can be a result of other types of pavement defects outlined
above. When a pavement cracks, water can enter the structure below
the pavement. This water then weakens the structure below the pavement
causing the pavement to fail.
Water can also enter below the pavement when the
shoulders adjacent to a road are not cleared to allow water to drain
from the pavement. In addition all pipes and ditches must be routinely
maintained to allow proper water drainage away from the road surface.
The key to correcting this type of failure is to
seal the cracks before they occur and clear shoulders, pipes and
ditches to ensure proper water drainage. If this type of failure
is not prevented, in most instances, this type of failure leads
to alligator type cracking which must be replaced and patched at
a cost of $16/sy.
Paved Road Degradation Over Time:
As a pavement ages the pavement develops cracks. If these cracks
are not sealed the pavement gets worse as described above. Over
time, the rate of pavement degradation increases (i.e. over time
cracking and base failure happens faster). As more cracks develop
more water gets below the pavement and the pavement failure increases.
Figure
2 illustrates the typical process of road condition changing
over time. As time progresses the road condition moves to a lower
condition in a less amount of time as shown in the steepness of
this graph. The costs shown in this figure at the various condition
levels are the estimated costs for resurfacing the road. As the
pavement condition worsens the costs to resurface increase dramatically.
This is described in much more detail in a later section of this
report.
The ideal time to resurface a road is when a road
is just past “good” condition prior to the condition
worsening to “fair” condition as shown in figure 3.
In this manner the road is brought back to the “excellent”
condition rating and the life of the pavement is renewed. In addition
the cost to bring this road to “excellent” at this point
is the lower than if the road is allowed to degrade further.
In this plan it is estimated that a pavement life
is 15 years. With 356 miles of paved road, Hart County should be
repaving 24 miles of paved road per year at an annual cost of over
$1,200,000. Because we have not repaved our roads in a timely fashion
some of our roads have degraded to fair, poor and very poor condition.
To bring all our paved roads to excellent condition is estimated
to cost Hart County $7,500,000.
The dilemma of how to plan for proper pavement management
is that all our paved roads are degrading in the same fashion. For
example if we resurface our all of our fair condition roads, our
roads in excellent, good, and poor condition will get worse and
more costly to fix. Taking care of our worst roads first may actually
worsen the overall paved road condition higher than the current
backlog of $7,500,000.
Excellent Condition Paved Roads:
Paved roads that did not have any significant cracking were ranked
as “excellent” condition roads. Fifty two percent (52%)
or 183 miles of Hart County paved roads were ranked in this condition.
A list of these roads is attached as appendix A.1.
The average life of a paved road is 12 years (including
years in “good” condition) and the GADOT reportedly
has a 10 year paving cycle. An optimistic estimate of a 15 year
pavement life was used in this plan including that an excellent
condition road will remain in excellent condition for 10 years prior
to moving to the next lowest conditional level of “good”
condition (with an additional 5 years in good condition).
Because the records of when roads were paved in
Hart County are very limited it is impossible to estimate where
an excellent condition road is in its life (i.e. when it was paved
last). Therefore this plan assumes that every year 10% of the excellent
condition roads will move into good condition (10 years=10%). Other
than routine maintenance as described in later sections, no work
is proposed for these roads.
Good Condition Paved Roads:
Paved roads where the pavement had less than 10% age cracking (T&L)
and less than 5% alligator/fatigue cracking were ranked as “good”
condition roads. Roads that had limited alligator cracking were
allowed to have a higher percentage of T&L cracking due to the
fact that the T&L cracking was apparently not leading to significant
alligator cracking. The lack of alligator cracking in these cases
indicates that traffic and base conditions are better than normal
and thus deserve a higher condition ranking.
Twenty five percent (25%) or 88 miles of Hart County
paved roads were ranked in this condition. Again a optimistic estimate
was applied that roads will remain in “good” condition
for 5 years prior to moving to the next lowest conditional level
of “fair” condition. A list of these roads is attached
as appendix A.2.
Because the records of when roads were paved in
Hart County are very limited it is impossible to estimate where
a good condition road is in its life (i.e. when it was paved last).
Therefore this plan assumes that every year 20% of the good condition
roads will move into fair condition (5 years=20%).
This is the ideal time to resurface a paved road.
At this point the cost for resurfacing using the road department
(including labor, material and equipment costs) is estimated to
be $47,374 per mile. Prior to overlay, all alligator cracking would
be removed by deep depth patching with asphalt (estimated to be
3% of road on average).
For the five year plan, the cost to overlay all
road in this category would be $4,168,912. This cost is too prohibitive
so the five year plan includes $30,976 for temporarily stabilizing
these roads by sealing all alligator cracking (at a cost of ($352
per mile,using a chip seal patching method). Other routine maintenance
so that water will not stand on the road is described in a later
section.
By sealing these roads it is assumed that no further
deterioration to the next level of “fair” condition
will occur during the planning period.
Fair Condition Paved Roads:
Paved roads that had 10-50% T&L cracking and 5-10% alligator
cracking were ranked as “fair” condition roads. Nineteen
percent (19%) or 68 miles of Hart County paved roads were ranked
in this condition. It was estimated that roads will remain in “fair”
condition for 3 years prior to moving to the next lowest conditional
level of “poor” condition. At this point the road has
developed significant overall age cracking and a fair amount of
road fatigue (alligator) cracking. A list of these roads is attached
as appendix A.3.
Because the records of when roads were paved in
Hart County are very limited it is impossible to estimate where
a fair condition road is in its life (i.e. when it was paved last).
Therefore this plan assumes that every year 33% of the fair condition
roads will move into poor condition (3 years=33%).
When roads reach this condition they have surpassed
the ideal time to be resurfaced. At this point the cost for resurfacing
using the road department (including labor, material and equipment
costs) is estimated to be $57,143 per mile or $9,769 more than roads
in “good” condition. If these roads had been resurfaced
just 2 to 3 years earlier when they were in “good” condition,
the costs for these 68 miles would have been $664,292 less.
The cost for bringing all these roads to excellent
condition would be $3,885,724. Because this is too prohibitive,
the five year plan suggests immediately stabilizing these roads
by sealing all fatigue cracking and major areas of other age cracking.
It is estimated that an average 38% of these road
surfaces will be sealed at a cost of $2,432 per mile labor and $1,298
per mile materials using the road department. This will consume
2,400 manhours of road department time in planning year 1. The total
cost will be $225,080 in materials plus $88,264 in labor and equipment.
However by sealing these roads it is assumed that
these roads will not deteriorate further to the next lower condition
rating of “poor” condition. Other routine maintenance
so that water will not stand on the road is described in a later
section.
A cost analysis of contracting the mass hauling
of materials has been performed. It costs taxpayers $3.95 per ton
in labor + $12 per ton in materials for the Road Department to haul
materials. If we hire a contractor to haul this material the total
cost is $13 per ton. An estimated 4,160 tons of stone will be required
for this work which will increase the material cost $4,160 however
this will save $16,432 in labor and equipment costs.
Poor Condition Paved Roads:
Paved roads that had over 50% T&L cracking combined with 10-20%
fatigue/alligator cracking were ranked as “poor” condition
roads. Only 3% or 11 miles of Hart County paved roads were ranked
in this condition. It was estimated that roads will remain in “poor”
condition for 2 years prior to moving to the next lowest conditional
level of “very poor” condition. At this point the road
has developed more significant overall age cracking and a larger
amount of road fatigue cracking. A list of these roads has been
attached as appendix A.4.
Because the records of when roads were paved in
Hart County are very limited it is impossible to estimate where
a poor condition road is in its life (i.e. when it was paved last).
Therefore this plan assumes that every year 50% of the poor condition
roads will move into very poor condition (2 years=50%).
The cost for resurfacing poor condition roads using
the road department (including labor, material and equipment costs)
is estimated to increase to $70,817 per mile or $13,674 more than
roads in “fair” condition. If these roads had been resurfaced
just 4 to 6 years earlier when they were in “good” condition,
the costs for these 11 miles would have been $257,873 less.
The cost to bring all these roads to excellent condition
would be $778,987. The five year plan suggests immediately stabilizing
these roads by sealing all fatigue cracking followed by 100% sealing
of the entire road and all other age cracking.
This will consume 1,200 manhours of road department
time in planning year 1. The total cost will be $95,810 in materials
plus $43,225 in labor and equipment. However by sealing these roads
it is assumed that these roads will not deteriorate further to the
next lower and very costly condition rating of “very poor”
condition.
The cost analysis of contracting hauling materials
is estimated to save the County $11,319 in costs.
Other routine maintenance so that water will not
stand on the road is also described in a later section.
Very Poor Condition Paved Roads:
Paved roads that had more than 20% fatigue/alligator cracking combined
with near complete age cracking were ranked as “very poor”
condition roads. Vanna road is 56% of the road miles in this category
and may be corrected this year. A list of these roads is attached
as appendix A.5.
Only 1% or 5.3 miles of Hart County paved roads
were ranked in this condition. When roads have deteriorated to this
condition the cost to patch this road is more than 75% of the cost
to completely reconstruct the road via a recycled base. Roads in
this condition have deteriorated too far and have significant base
problems where the structural base will not support a new surface
course and should be replaced prior to resurfacing.
If these roads are resurfaced without correcting
the base problem, the new asphalt will only last a few years before
it begins to fall apart again. This plan presents three options
for roads in this condition.
The first option is to tar and gravel these roads
at a total cost of $157,830 in labor and materials using the road
department. This option may meet with strong opposition from the
residents and may not solve the problem of a poor base.
Option #2 is to reconstruct the base by milling
the existing asphalt and adding additives to strengthen these materials.
This new base is then asphalt surfaced. The total cost for this
option is $638,930 using all contracted services. The Road Department
could perform the resurfacing and reduce the cash costs (materials
only, not labor) by $130,000.
Option #3 is to reconstruct the base by milling
the existing asphalt and adding new stone base materials. With this
option we may have to remove some materials below the road to lower
the road elevation prior to adding new base materials. With this
option the roads have been divided into two classes depending on
the anticipated truck traffic. Lower truck traffic roads are assumed
to need only 4” of stone materials.
Option #3 would cost a total of $621,188 for both
labor and materials using the Road Department (contract milling).
Material cost only are (and contract milling costs) are $400,390.
5 year plan for paved roads
Year 1:
The cost to repave all roads in good, fair, poor and very poor condition
is estimated to be $7,500,000 in materials (not including labor
and equipment costs). Because this cost is too excessive for the
planning period, in the first year (FY03) the plan suggests stabilizing
our roads so that further pavement degradation is minimized. As
stated above all roads are continually degrading to a more costly
rehabilitative condition with the exception of the very poor condition
roads.
As shown in figure 3 above (“Do Nothing (Mtl.
Costs)), if we take no action on our paved roads, our paved roads
will degrade further and our current debt of $7,500,000 may grow
to almost $15,000,000. By stabilizing all roads it is assumed that
no further degradation of our paved roads will occur. Therefore
it is assumed that these stabilized roads will remain in their current
condition rating during the five year planning period.
Currently we use a duropatching or spot chip seal
method to temporarily patch our roads. This very cost effective
procedure is recommended to be expanded so that all our good condition
roads are sealed.
This plan recommends using a chip seal for the fair
and poor condition roads in year 1. While this procedure is very
cost effective it does have negative drawbacks. The resulting surface
is rougher than asphalt and some loose chips (stones) may be temporarily
evident.Roads
in fair condition are proposed to be sealed only where deterioration
has occurred in strips or large patches (estimated to be 40% of
the road surface). These patches are too large to use our current
duropatch procedure. Poor condition roads would be sealed at all
alligator cracking followed by 100% surface sealing.
If we
embark on this proposed ambitious road sealing plan we need to plan
on replacing our existing gravel spreader. As used gravel spreader
will cost about $45,000 and a new one $90,000.
We are proposing an alternate
method that will result in significant labor and equipment savings.
We propose to purchase three box spreaders that will attach to our
existing tandem trucks. These three boxes will cost less than $15,000.
With the box spreaders
we will eliminate the need for a separate spreader machine costing
$45,000-90,000 to replace as well as three operators for this spreader.
This is estimated to save $20,000 in labor costs alone the first
year.
Total material costs
(FY03) for sealing our roads is estimated at $387,748 and would
consume 3600 manhours (15% of annual Road Department manhours).
However again it is assumed that if we perform these sealing tasks
in year 1, the cost to bring all paved roads to excellent condition
will stabilize at $7,500,000 through the five year planning period.
While options
have been presented, no plans have been included in this report
for roads in very poorcondition. Roads in this condition will have
to be evaluated to determine what to do (tar and gravel or rehabilitate)
and how much of an investment to make.
Planning Year 2-5:
In planning year 2-5, Hart County should concentrate on an investment
to resurfacing our paved roads. Any investment in our paved roads
will reduce the current debt of $7,500,000. Using resources for
converting dirt roads to paved roads or other diversion of resources
will result in an increasing debt at the end of the five year planning
period.
TAR AND GRAVEL ROADS
Hart County
has 92 miles of tar and gravel road with a replacement value at
2002 dollars of $3,220,000 (based on a contract replacement cost
of $35,000/mile). According to the records, these roads have never
been resurfaced and consequently are past their design life. Twenty
two percent (22%), or 20 miles have degraded to the point where
at least two applications of new chip surface will be needed.
Combining the 92 miles
plus 20 miles needing more than one surface treatment results in
112 miles of new tar and gravel surface treatment needed now. This
plan recommends that this work be performed using the road department
over the 5 year planning period. Therefore 23 miles of resurfacing
of tar and gravel roads is proposed each year for 5 years. Resurfacing
is similar to chip sealing.
Contracting
this work would cost $15,000 per mile for a total cost over the
planning period of $1,680,000. If we perform this work using our
road department and our existing equipment our cost per mile is
estimated to be $3,417 (labor and equipment) consuming 88 manhours,
plus $6,400 in materials for a total of $9,817 per mile or $1,099,504
over the five year planning period.
Assuming labor and equipment
is funded through general fund and materials are funded through
SPLOST, the annual SPLOST allocation would be $147,200 each year
for five years.
Contracting hauling of
materials to our stockpile at the Public Works Complex will save
$7,590 in materials and $15,000 in labor annually for our tar and
gravel road work. (23 miles of tar and gravel 165 tons per mile,
3,795 tons per year)
At least 20 miles of
our tar and gravel roads are showing significant degradation and
an additional 43 miles are showing advanced signs of wear. Only
29 miles of tar and gravel roads are showing minimal sings of significant
defect other than the loss of the surface course.
As shown in
figure
4, if no action is taken on these roads during the five year
planning period it is assumed that 100% of the 20 miles (significant
degredation) and 50% of the 43 miles showing advanced wear will
be totally lost. This would result in a loss of 42 miles of tar
and gravel roads at a replacement cost of $1,452,500 today over
the five year planning period (lost asset value).
The remaining 49 miles
will still need resurfacing at a cost of $440,784 with a residual
asset value of $1,400,000. In contrast with this plans recommendation,
our five year investment of $1,028,500 will bring our tar and gravel
road asset value up to $3,220,000 and our debt (liability) to $0.
OTHER FACTORS
Maintenance of Paved
Roads:
The pavement on a paved road is similar to a roof on a house where
both must shed water to protect the structure below. If water is
allowed to get below the pavement it weakens the structure below
the road causing the pavement to fail.
Roads develop cracks
from natural and manmade forces as the pavement ages. These cracks
allow water to enter below the pavement causing additional fatigue/alligator
cracking. When fatigue cracking occurs, this area must be removed
and replaced prior to resurfacing.
The goal is to minimize
the amount of water getting below the pavement. This is done by
both sealing cracks when they occur and by ensuring that road surfaces
drain properly and do not allow water to stand on the road.
Sealing every crack on
our County roads would be very labor intensive. The five year plan
addresses a mass sealing of a majority of the cracks in the first
year. It is important that we seal all fatigue cracking on an annual
basis to minimize the spread of this fatigue cracking.
The other important factor
is to keep water from standing on our roads. As vegetation grows
on the edge of the pavement, it increasingly prohibits water from
leaving the road surface. To correct this problem the shoulders
and ditches must be scraped on a routine basis. This also makes
our roads safer by not allowing water to puddle on our roads creating
unsafe driving conditions.
In addition,
as vegetation grows on the side of the road it will grow into the
pavement if traffic does not travel on top of it. In some situations
several feet of pavement is covered with vegetation. This vegetation
will root into cracks and force apart the asphalt below causing
further degradation of the asphalt road surface.
See
figure 4
We are proposing a 3
year cycle for our paved roads whereby we clear the shoulders, ditches
and pipes every three years. Therefore we would we “clip shoulder”
one third of our paved roads annually consuming an additional 6,440
manhours per year.
Some of our roads also
need paint stripping. It is estimated that paint stripping will
last 5 years and must be redone every five years. At a minimum (depending
on the class of road, ,i.e. amount of traffic) some roads should
be striped while others (low traffic) could remain unstriped. Additionally
a minimum those roads that are to receive stripping should have
the center yellow stripes painted. Some roads may warrant addition
side stripping (white). An annual allocation should be budgeted
each year for stripping.
For this plan it is assumed
that 25% of our paved roads (including tar and gravel) will need
stripping. This amounts to a total cost of $100,000 spread out over
5 years.
Maintenance
of Gravel Roads:
Hart County currently has approximately 109 miles of dirt road (gravel
surfaced roads). These roads develop potholes, washboards, loss
of stone and other conditions which make travel difficult. These
roads should be maintained by scraping and placing new stone on
a periodic basis. On
average it takes about 3 hours to maintain one mile of gravel road.
We also place an average 23 tons of new gravel per mile. With 109
miles of gravel roads we would consume 1962 manhours per year.
Table
3. Annual Allocation of Road Department Manhours
Utilization of Road Department Resources
The road department has 14.4 men. With annual leave including sick,
vacation, holiday combined with vacant positions, it is estimated
that 25,456 manhours are available annually. As shown in table 3
and figure
5, these manhours are consumed by many tasks.
Since August
of 2001 the road department has been tracking time utilization for
various tasks. This data was analyzed to determine how many manhours
were used or needed to produce various work products as described
below and in table
3.
Tar and gravel resurface
over the five year planning period will consume 2,024 (8%). Sealing
our paved roads (“fair” & “poor”) consumes
3,600 (14%) manhours in planning year 1.
As described
in this plan the key function to preserving our paved road assets
is eliminating water from ponding on our roads by clipping the shoulders
and clearing the ditches and pipes. This work will consume 6,440
(25%) hours annually.
Duropatching,
a process described earlier in this report of spot chip sealing
fatigue cracking and potholes costs $0.50 per square yard and saves
many fold more in preservation of asphalt. This process will use
1,617 (6%) manhours annually. Our dirt roads should be maintained
by scraping potholes and other maintenance tasks which is estimated
to need 1,962 (8%) manhours annually. Placing and maintaining signs
uses 480 (2%) manhours annually. Placing driveway and pipes uses
575 (2%) manhours annually. Miscellaneous work primarily picking
up trash and other tasks such as landscaping and other requested
work is estimated to use 1,990 (8%) hours annually.
Each year we
must work on roads that will be funded through LARP. This work involves
both patching and reworking of shoulders after paving and will consume
1,035 (4%) manhours annually. Similarly work on maintaining our
closed landfill uses 400 (2%) each year and clearing beaver dams
320 (1%) manhours.
The balance
of Road Department manpower resources is also shown in this table.
If we properly manage our roads this is the proper allocation of
manpower resources. “Unallocated” manhours are available
for other projects. Allocation of manpower resources above this
“unallocated” amount will detract from proper maintenance
of our roads and will increase our current $7,500,000 paved road
debt. We
should review the manpower allocations presented in table
3 and determine how we desire to allocate our resources. This
should be evaluated on a periodic basis so that we can reallocate
resources as needed.
First Time Paving, Pave
Roads vs. Gravel Roads:
Maintaining a gravel road by scraping that road two times per year
and placing an addition 23 tons of gravel per mile costs a total
of $492/mile per year.
In comparison to first
time paving, it costs 20 times or $10,000 per year annually for
the first life cycle of a paved road when that road has been converted
from gravel to paved. On average it costs $150,000 to convert a
dirt road to a paved road. That pavement should last 15 years.
Pavement on an existing
paved road should also last 15 years. The average cost per mile
per year during a paved roads life cycle is $3,400.
Cost to Maintain a gravel
road $492 (per mile per year)
Cost to Maintain a paved road $5,000 (per mile per year)
Cost for first time road (first life cycle) $10,000 (per mile per
year)
Bridges/Live
creek Crossings
While inventorying and determining the condition of Hart County’s
paved roads, bridges (live water crossings) were also inventoried
and condition evaluated. This list is fairly comprehensive but may
have missed some crossings. 220
crossings consisting of concrete pipes, metal pipes, concrete bridges,
steel bridges, concrete box type culverts, wood bridges and a few
fords have been identified. Of these over half 119 need some type
of work performed. Approximately half of those that need work have
been placed on a GADOT list advising the County to take actions
to fix problems with our bridges.
A more comprehensive
report on our bridges will be developed in the near future. Costs
for this work will be estimated but may run as high as $10,000-$100,000
per crossing and in aggregate could be over $1,000,000. |