Hart
Roads Planning Session
The Hart County Board of
Commissioners met
Present: Chairman Joel Moore, Commissioners Ken Brown, Don Burdick
and Harry Hannah,
Chairman Moore called the meeting
to order at
Chairman Moore reported that the
DOT contract document for
Ridge Road Project was discussed as to whether it should be done in-house or by contract. Commissioner Burdick said it didn't matter to him as long as we started the job. His concern was the potential lose of funding if we do not proceed. Public Works Director Haney supplied the following cost estimates.
In-house $43,800 $108,800 $152,600
Contract $98,300 $108,800 $207,100
LARP Projects
Existing contract with E. R.
Snell will require a change order for about $4,000 to remove abutments. They
expect to start the project
At DOT awaiting their response.
Schedules:
·
It is expected that all non-standard roadwork,
including
·
Assuming that the
· Kings Bench Project estimated at 6 - 8 weeks
· Ridge Road Project estimated at 6 weeks
·
Other Projects
·
Ownership
documents to be sent to the
· Road Adoption Policy
Discussion was held on amending the Road Adoption Policy to address how many property owners were necessary along a road as criteria for adoption
· Romeo Adams property on CR127
CR127 does not show its true length on the DOT maps. DOT will be requested to change the map. Mr. Adams would like the county to maintain it ditch-to-ditch road up to his property
Project Costs & Projected Expenditures
Rick Haney went over a spreadsheet showing estimated total costs for the non-standard road projects to total $380,3223.23.
Meeting
adjourned at
----------------------------------------------- -------------------------------------------------
Joel Moore,
Chairman Gary S.
Cobb,